Public hearings on the preliminary environmental impact assessment of the construction and operation of the 1st and 2nd units of Nizhniy Novgorod Nuclear Power Plant took place in Navashino, Nizhniy Novgorod region on Sept 4 2009.
Quite a big part of the energy to be produced by Nizhniy Novgorod Nuclear Power Plant will be supplied to sub-stations of Vladimir region. Presently, both Nizhniy Novgorod and Vladimir regions are short of energy and are unable to effectively develop their industries.
Lack of energy curbs not only industrial development but also housing construction. Nizhniy Novgorod NPP will become a powerful source of energy and will stimulate growth in both Nizhniy Novgorod and Vladimir regions.
Nizhniy Novgorod NPP is a serial project. A similar project is presently being implemented at Novovoronezh NPP-2. The general designer is Nizhniy Novgorod Atomenergoproekt (part of Atomenergoprom), the owner is Energoatom Concern OJSC (100% subsidiary of Atomenergoprom OJSC).
The plant will have two 1,170MW reactors and will generate over 17bln KWh a year and employ as many as 1,000 people. At the peak time the construction will involve as many as 8,000 people. The 1st reactor is supposed to be launched in 2017. The plant will be situated in Navashino district of Nizhniy Novgorod region.
The analysis of the power and capacity balance in Nizhniy Novgorod region has shown that in 2007 the region was short of 1,800MW while in 2020 it will need as much as 4,000MW.
This is a socially significant project: it will give the region 40bln RUR in profit tax, 50bln RUR in property tax, 1bln RUR in land tax and 50bln RUR in transport tax.